Log time without having to adjust Remaining Estimate. Possible?

Robert
Contributor
September 2, 2015

Hi,

I would like my team to be able to log time spent, without seeing also the options for Remaining Estimate. Is it possible?

Thanks.

Robert

2 answers

1 accepted

0 votes
Answer accepted
Jobin Kuruvilla [Adaptavist]
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
September 2, 2015

You will have to develop a custom issue operation that does that. Default 'Log Work' operation in JIRA requires you to pick one of the many options to update remaining estimate.

0 votes
Robert
Contributor
September 2, 2015

Thanks