Kim Loudon April 21, 2025

I'm trying to create subtasks via csv upload. I was able to do so in this project in March but now when I try to upload with the same file I used before I don't see an available mapping for "parent". Then I get an error message stating a Parent Issue Key or ID wasn't specified. Did something change in the last month?

3 answers

1 accepted

1 vote
Answer accepted
Andy Heinzer
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
April 23, 2025

Hi @Kim Loudon 

I understand that you have been using the bulk creation to import subtask, but that this is no longer providing the option to set the parent value when doing so.  It was my understanding that the bulk create wasn't able to set the parent value.  And in turn it was something we expect to the External System Import to be able to do, although that does require the user to be a Jira Admin to use that tool.

That said, I did come across a recent bug over in JWMCLOUD-881.  Which would seem to indicate that Team-managed Business type projects are specifically affected by this limitation/defect.  Which would indicate that perhaps the bulk create has been able to set the parent value in company-managed projects.

Are you using a team-managed project for this particular import?

Sorry there doesn't seem to be an easy fix yet.  In the meantime, I'd recommend reaching out to a Jira Admin so that they can use the External System Import utility in order to create these subtasks instead.

Kim Loudon April 23, 2025

Hi Andy, 

Yes this is a team-managed project. 

Like Tomislav Tobijas likes this
0 votes
John Funk
Community Champion
April 21, 2025

Hi Kim - Welcome to the Atlassian Community!

Are you going through the route of Settings > System > External System Import? 

If not, try that. If you are not a Jira Administrator, have your Admin try it. 

Kim Loudon April 21, 2025

Hi John, 

I am going to All work>Ellipses menu (...)>Import Issues from CSV. 

I'm not a Jira admin but have been able to import this way as recently as last month. I still can import tasks this way but seems I'm not able to do subtasks anymore as there is no mapping for the parent field. 

John Funk
Community Champion
April 21, 2025

Yes, this seems to be some that Atlassian has changed recently for some reason. Until there is a change back, if at all, you will need to have a Jira Admin run the import. 

John Funk
Community Champion
April 23, 2025

So, based on Andy's comment - is this a Team-managed project or Company-managed project that you are trying to import into? 

John Funk
Community Champion
April 23, 2025

So, since it is a Team-managed project, and there is a bug, you will need to go through the System route as outlined above by the Jira Admin. 

0 votes
Tomislav Tobijas
Community Champion
April 21, 2025

Hi @Kim Loudon ,

I'm not sure if there were any backend changes recently related to CSV imports. I can see that available (system) fields for parent import are "Parent" and "Parent Link".

2025-04-21_20-30-08.png

I guess you could try adding the parent ID into 'parent' column in CSV and then map it to "Parent" field.

I'll ask someone from Atlassian to jump in here to maybe give some insight on the matter.

Cheers,
Tobi

Kim Loudon April 21, 2025

That's what I've had before but it appears to not be there any more. 

 

parent issue.jpg

Like Tomislav Tobijas likes this
Ricky Strohmeier
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
April 23, 2025

In our jira instance, we also have the problem that fields are missing during csv import. for example, the field for the “Vorgangs ID”. Is there a solution for this soon? We can no longer perform csv imports that contain an assignment of sub-tasks to tasks.

Tomislav Tobijas
Community Champion
April 27, 2025

Hi @Ricky Strohmeier ,

Are you also using team-managed project/data import? If so, please see Andy's answer.

Otherwise, we'd probably need some additional info about how you are trying to do the import, what field type is "Vorgangs ID" and such.

Ricky Strohmeier
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
April 28, 2025

Hi @Tomislav Tobijas ,

it is different here. I am already doing the import as an admin from its certain view. I guess "Vorgangs ID" is "work item id". At least it is where I am mapping "Übergeordnet" (must be the German equivalent for "parent") to. "Vorgangs ID" is no longer there but "work item id" is. Everything worked perfect until lately. Sub-Tasks are no longer imported and I did not change the way of doing the import. Do you have any guesses what could help?

Thank you!