Activity TimeLine / Jira Integration Synchronization problem

jbh5310
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
February 27, 2021

Hi.

I have an issue with the Activity Timeline. It started recently but it is not being used.

Project and user information is does not sync.(I use an administrator account. And I use crowd Server)

1. User sync.

   - There are 4 accounts in User Management.

   - I set it as below, but it is not synchronized.

   - Jira group also does not sync.

UserSync.png

 

2. Project sync.

    - Like user information, it cannot be synchronized.

projectlist2.pngprojectlist1.png

 

 

How should I set it?

Please help.

 

Thank you.

 

**version

jira-server : 8.15

active timeline : 8.1.0

1 answer

0 votes
Ostap Zaishlyi _Reliex_
Atlassian Partner
March 1, 2021

Hello @jbh5310 

Thanks for the question!

 

So this could occur due to the interruption in the Setup Wizard Synchronization.

 

All you need to do at this point is to go to ActivityTimeline Configuration (using Jira admin account)->Setup Wizard-> Go through the Setup Wizard process again and wait until  the system fully synchronizes:


Setup Wizard.png

This should help you.