Is there an option to make dependent (blocked) tasks move on the timeline, if i move a task that blocks it?
For example: A blocks B. A is moved on the timeline by two weeks. So B should move on the timeline by two weeks, too.
Hi Anne-Sophie - Welcome to the Atlassian Community!
No, I don't think the dependent linked task will also move because it is not assumed that the timing is the same, just that they are dependent. But you might could do this with automation - changing the Start Date (or Due Date) of one issue if the linked issue Due Date changes.
Hello @John Funk
Thanks for this idea. How to implement this kind of automation. Sorry, but I'm new to JIRA automation. Thanks in advance
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Raimund - Welcome to the Atlassian Community!
It's better to open a new question, then more people can help with it.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi everyone and @Anne-Sophie Riemer-Harms
I am reaching out to invite you to participate in an interview regarding the Jira timeline view feature. I would like to further understand your needs around moving dependent tasks on timeline.
The interview will take approximately 60mins and can be scheduled at your convenience. If you are interested in participating, please schedule a time with me via this link with your availability.
Thank you for considering this opportunity to share your thoughts!
Best regards,
Amy Cheong
Senior Product Manager, Atlassian [Linkedin]
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
i was struggeling with that issue for a long time too, until I accidentially found out this:
When you link your tasks use "has to be done before/after" instead of "blocks/is blocked". When you move the tasks on the timeline afterwards, the following tasks will move accordingly.
It would be great, if atlassian lets the user choose the default connection of the tasks, when connecting them graphically with the line in advanced roadmaps.
hope I could help,
Johannes
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.