Bulk update a link "blocked by"

Juan du Toit February 26, 2017

Hi There,

 

I have about 3 Epics that are blocked by about 200 issues.  

I want to do a bulk update in JIRA to link all those 200 issues to the 3 Epics  (If even possible) 

I want to do this so that it shows in Portfolio that those 3 epics can only be done if ALL the work has been completed.  

As this is an unusually large number, I want to know if there is maybe another approach that I can should try?

 

Regards,

Juan

1 answer

0 votes
Roman Samorodov
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
February 27, 2017

The only way is to search for all theese issues using custom jql function created by yourself or found in plugin. Then use bulk change for them.

Trudy Claspill
Contributor
April 18, 2018

Bulk change doesn't support changing, adding, or removing Issue Links.

Like • Julian Kühnel likes this

Suggest an answer

Log in or Sign up to answer
TAGS
atlassian, team ’25 europe, early bird extension, conference discount, barcelona, hybrid event, AI teamwork, early bird pass, digital access, collaboration conference, atlassian events, register now, developer conference

1 week left to save on your Team '25 Europe pass

Still thinking about joining us for Team '25 Europe? Early bird has been extended for just one week! Now’s the time to lock in your lowest rate. Use code TEU25COMM-20 to save 20% at checkout. Hurry, this only lasts for 1 more week.

Learn more
AUG Leaders

Atlassian Community Events