I mistakenly accepted a change to my Kanban board and now the backlog column is no longer a part of the board. Is there a way to add it back? My team prefers to see the backlog items on the board versus having to navigate to another view to access these items.
Hello - Go to your board that you want to change, click Board > Configure and go the to Columns tab. You should be able to drag the 'workflow-status' from the Kanban backlog section into an actual column. You may have to 'Add column', name it backlog and then drag your status over.
Hope this fixed your issue! Thanks!
This instruction was incorrect. It should be:
Kanban Board > Click the ... in the upper right of the board > Board Settings
Then drag the Backlog status block into the Backlog Status column (or create if needed).