Just a few questions:
How did you automate it (rest/scheduler/active batch)?
What did you automate?
How often did you schedule it?
What is the full error, where did you see it?
What JIRA are you using (server/cloud)?
Hi ,
i have a first automation who copy the component on the summary.
and a second one whe the issue is updated to copy the new component on the summary.
the error message is Possible loop detected! Rule 'Update Request Participants list when issue edited [test]' was executed more than '20' times in last '500' ms..
I am using JIRA server
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I did some more testing it seams like the loop is started because i have 2 rules that run on Issue Updated. This does not make sense because both are supposed to run if 2 different JQL queries are met. If i disable one of them then everything runs fine.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.