Just a heads up: On March 24, 2025, starting at 4:30pm CDT / 19:30 UTC, the site will be undergoing scheduled maintenance for a few hours. During this time, the site might be unavailable for a short while. Thanks for your patience.

×
Create
cancel
Showing results for 
Search instead for 
Did you mean: 
Sign up Log in

How do I create a sprint in the past.

Todd Rinaldo August 27, 2012

I've imported my user stories from another system, but I cannot seem to add them to a sprint dated in the past. I get the error: "You must specify a start date that is not in the past.". How can I work around this to import past sprints?

2 answers

1 accepted

1 vote
Answer accepted
James Sandlin August 27, 2012

Create a sprint NOT in the past. Drag your tasks into said sprint. Update said sprint to be a past date. Close said sprint.

Todd Rinaldo August 27, 2012

Yep. I'm trying to import 10 sprints from another system.... PAINFUL!!!!

Jeff Isenberg
Contributor
October 23, 2012

This doesnt work for me as the end date always gets updated to the current date when I close the sprint, even though I set it to a past date.

0 votes
Jeff Isenberg
Contributor
October 1, 2012

Is there any way to use bulk update?

Suggest an answer

Log in or Sign up to answer