How do I get a working point estimate field back?

Abby Wooden
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
December 4, 2018

We were having an issue as a team with multiple point estimate value fields, with only one that actually added everything up in our sprint/backlog view, calculated burndown, etc. 

The team was accidentally using the wrong fields to add points resulting in issues with estimates. I cross-checked which field seemed to be actually adding things, and then deleted the extra one. Unfortunately, I must have somehow chosen the wrong one, as now all our points are gone and no longer calculating capacity, burndown, etc. 

I know I can't get back the point values I lost, but how do I get the locked JIRA "Story Point Estimate" field to do the calculations and show in the backlog view as before? I've been trying for quite a while and unable to figure this out. I want the points to show again on each card and added up on the top as circled in red below: 

Screen Shot 2018-12-04 at 10.27.46 AM.png

 

Thanks! 

1 answer

1 accepted

1 vote
Answer accepted
Morgan Folsom
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
December 4, 2018

Hi Abby,

For each board, you can select the field to be used as the Estimation Statistic.You can simply go to Board Settings -> Estimation

Cloud (Scrum or Kanban): https://confluence.atlassian.com/jirasoftwarecloud/configuring-estimation-and-tracking-764478030.html

Server(Scrum Only): https://confluence.atlassian.com/jirasoftwareserver/configuring-estimation-and-tracking-938845319.html

 

Hope that helps - let me know if that doesn't get you what you need!

 

Morgan

Abby Wooden
I'm New Here
I'm New Here
Those new to the Atlassian Community have posted less than three times. Give them a warm welcome!
December 6, 2018

Thanks! That worked perfectly, and much simpler than I expected! 