How to add time estimate, time logging, time tracking fields currently present in task into EPIC?

Ankit Goyal October 24, 2018

How to add time estimate, time logging, time tracking fields currently present in task into EPIC?

1 answer

0 votes
Divya Suseelan October 24, 2018

1. JIRA Settings > Issues > Issue Features > Time Tracking

Enable Time Tracking and modify the time tracking settings as applicable.

2. JIRA Settings > Issues > Fields > Field Configurations

On the Field Configuration settings, choose the applicable Field Configuration. You will find the field name 'Time Tracking'. Add the screen names that is relevant to the issue type EPIC.

This way time tracking can be enabled.

Ankit Goyal October 24, 2018

@Divya Suseelan Thank you for your reply. I could not find time estimate field.

Divya Suseelan October 25, 2018

@Ankit Goyal Are you using Next Generation Project? If yes, Time tracking isn’t there yet but is planned.