Hi,
We are just starting to evaluate JIRA Portfolio for planning our roadmap and I am not really sure how outsourcing teams should be handled. For example lets say we have a project that has an estimate of 500 hours out of which 400 hours will be developed by an outsourced team which does not have access to JIRA.
Prior to portfolio we would only create the 100 hour task in JIRA but now that we want to have the roadmap in portfolio having the outsourcing time should be considered.
Has anyone else run into this scenario? What is the recommended approach?
Thanks for any insight!
Tudor
Hello,
You can create a new team, and assign "virtual users" that would be taken into account as "outsourced team members".
More information here.
Cheers,
Maria
Portfolio Tech Writer
Thank you Maria, I completely overlooked the virtual users option!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
AI-powered meeting notes keep work moving even if you’re out of the office. Enjoy your well-deserved time off and return refreshed, confident you’ll catch up in no time.
Learn more
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.