Hello Team,
In my current sprint when I see the sprint report I see for all the story's/issues I have added to sprint showing "Story-ARV-4 *-Issue added to sprint after start time" .
But after the sprint has started I did not added any new story/Issue or sub tasks under them..but still I am getting this * mark against all the issues in the board
Hello Aravind
This can be due to updating the original estimate of an issue after sprint started.
have you updated estimate of that story?
Hi Mhasan, no I didn't update original estimate ,surprisingly "*" is highlighting against all storys that I have added in sprint.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
so another posibility is that you have set the start date of the sprint to an earlier time that day or another day in past,
for example you have added tasks to sprint in 12:00 and then started the sprint, but when starting the sprint you have set the start hour to 10:00. in this case all the tasks would be marked as stared (*) in the sprint report.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.