Here should be my hierarchy as per my requirement
Epic
Story
Tasks
Sub tasks
But I an not being able to make task under story as child instead it is only allowing to to directly making sub-tasks (there is no option of making tasks under story
Hi Ghulam - Welcome to the Atlassian Community!
First, you will not be able to modify the Issue Hierarchy to add new levels on a Free account.
And second, you should not be nesting Tasks under Stories - that is not standard Agile practice. They are at the same level.
Welcome @Ghulam Sarwar
If you are using premium version of Jira, you can indeed change the hierarchy and even modify it by your preferences.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
see this thread for a comprehensive discussion on the matter and possible ways forward.
Hope this helps,
Best,
Hannes