I have 6 columns on my Kanban Board. For the sake of simplicity, let's call them c1, c2...c6. I would like to generate a report (or graph) that tells me how long it has taken for each Story to move from c2 to c5. Is this possible using the out of the box chart/report? If not, any workaround will be appreciated.
Hi,
This is easy to do, just go to the Control Chart in the Report section. In the 'Refine...' button select the states for which you want to calculate the time spent in those states. For example, if I select c3 & c4 it will show me the average time issues have spent going between c2 and c5.
Cheers,
Shaun
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Shaun,
Can you please let me know how the REOPEN is treated by the report? For example, a REOPEN results in moving the issue back to the left columns, and has to make it to right once again. I think the solution would be to group by the transition states and SUM the time spent in each. Is the report doing that?
Thanks,
Deepak
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.