I estimated my issues, but when i log work on them, i can log more hours than my estimation. Is there any way to restrict that?

2 answers

1 accepted

0 votes
Answer accepted
Warren
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 16, 2017

The short answer is NO - see Only-allow-time-tracking-if-original-estimate-is-not-reached for a similar question and it's answers

0 votes
Nikola Velevski
Contributor
August 16, 2017

Thanks @Warren

Suggest an answer

Log in or Sign up to answer
TAGS
atlassian, loom, AI, meeting recording, community

[NEW] Record your meetings with Loom

Welcome to great meetings, with less work. Automatically record, summarize, and share instant recaps of your meetings with Loom AI.

Learn more
AUG Leaders

Atlassian Community Events