Hello, 

is it possible to move all tasks and stories from an epic to a sprint? We often have the requirement to develop a whole epic in a sprint, so this would be a nice feature. 

 

Best regards,

Peter

1 answer

1 accepted

5 votes
Answer accepted
Jakub Lazinski
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
April 13, 2017

Hey Peter, how about:
* filtering issues in your backlog by the Epic you're interested in moving to a Sprint; you can do it by using the Epics tab on the left hand side
* once filtered out, select all issues in Backlog
* right click on any of them and select Move to Sprint

Suggest an answer

Log in or Sign up to answer
TAGS
atlassian, mindful member, mindful member badge, atlassian community, community kudos, community giveaway, atlassian swag, community values, empathy and kindness, badge challenge, atlassian learning, community engagement, swag giveaway

Earn a Badge, Win a Prize 🎁

Earning the Mindful Member badge proves you know how to lead with kindness, plus it enters you into a giveaway for exclusive Atlassian swag. Take the quiz, grab the badge, and comment on our announcement article to spread the good vibes!

Start here
AUG Leaders

Atlassian Community Events