Hi All!
When I move an issue from the Active Sprint to the Backlog (Using Move to -> Backlog by right-clicking the issue in the Board), in what position does the issue gets moved into in the Backlog? I see that it's always not moved to the Top/Bottom of the backlog. Does this depend on the Rank of the issue?
The backlog is usually set to ordered by rank. i.e. to keep the order you have placed them in. An issue added with an existing rank value will be placed according the that value. The position is dependent on the the history of your items in setting a rank value.
The rank value isn't visible and it's not a simple number. An issue may be displayed on multiple boards so the value is a complex string.
The is an issue raised here you can vote for
Hi @Tom Lister
Thank you for the response and it clears the query I had on the ordering. Also, a human-readable rank would be very useful and I have voted for the same.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi @Rajalinga Pandian I have attached a image below . you have to navigate to the backlog section and in the active sprint whichever issue is there you need to drag and drop in backlog .
I think this might help you :)
thanks ,
Rishav
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Atlassian Government Cloud has achieved FedRAMP Authorization at the Moderate level! Join our webinar to learn how you can accelerate mission success and move work forward faster in cloud, all while ensuring your critical data is secure.
Register NowOnline forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.