Original Estimates for items in "To Do" status is 0- In Backlog

Aleena Umaiir
Contributor
July 10, 2024

In the backlog, where we can show the estimations for tasks, original estimations for 'In progress' & 'Done' tasks is correct, but for "To Do" it is showing zero, although I have many tickets with in "To Do" status with original estimates added. 

2 answers

1 accepted

0 votes
Answer accepted
Trudy Claspill
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
July 15, 2024

Hello @Aleena Umaiir 

Can you show us the mapping of Statuses to Columns in your board view?

I recall that there was some limitation to how the gray lozenge summarizes information. I'm looking for that information. As soon as I find it, I'll add another response.

Trudy Claspill
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
July 15, 2024

I found the reference. While it talks about story points it might also apply to time estimates.

Check if this description matches your experience.

https://confluence.atlassian.com/jirakb/estimation-of-story-points-observed-on-the-backlog-does-not-match-the-status-category-1381826620.html

Aleena Umaiir
Contributor
July 17, 2024

It actually helped @Trudy Claspill , my leftmost column has no status assigned and it was not TO Do, I removed that, and now my leftmost is TO DO, with its respective status and it's showing the estimations. 

Thanks again!

Trudy Claspill
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
July 17, 2024

I'm glad I could help you.

If my response helped you solve your problem please consider clicking on the Accept Answer button to mark you post as Solved.

Jack Brickey
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
July 18, 2024

Hi @Aleena Umaiir , sorry for not getting back to you. I disappeared on vacation. I have deselected my response as "accepted" as it was incomplete and did not provide the answer. I have selected Trudy's answer as accepted as I believe it accurately presents the solution. If you feel otherwise please deselect and let us know.

Aleena Umaiir
Contributor
August 15, 2024

@Jack Brickey No problem, it got answered initially to some extent and @Trudy Claspill  helped me. 

But I want to know another thing, in my case, it only shows estimations for the stories and not for the sub-tasks in the stories.

For example, if there is a story in To-Do with 2 days estimation, and one of its sub-tasks has an estimation of one day and that sub-task is in In-Progress. 

It only shows 2 days estimation for the story and does not show One day time estimation for the sub-task which is in In-Progress. 

Explained in the below example

Example.PNG

Trudy Claspill
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
August 24, 2024

Hello @Aleena Umaiir 

Those totals will include only the standard (level 0) issues like Story, Task, and Bug. That is per design by Atlassian, as mentioned by an Atlassian Team Member in response to this post.

https://community.atlassian.com/t5/Jira-questions/How-can-I-get-my-subtask-time-estimates-to-be-displayed-and-be/qaq-p/1091999

To include the times from sub-tasks in those totals you would need to roll up the time information from the sub-tasks and add that into the time information of the parent issue.

Aleena Umaiir
Contributor
August 26, 2024

Thanks @Trudy Claspill ,

Well, it will be helpful if Atlassian allow us to view estimations on sub-tasks level too.

Trudy Claspill
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
August 26, 2024

They don't appear to be interested in providing that functionality. 

You might consider contacting Atlassian Support about having a change request opened and/or providing that feedback to Atlassian through the Feedback option under the Help menu within Jira 

0 votes
Jack Brickey
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
July 10, 2024

Hi @Aleena Umaiir , can you share a screenshot of where you are observing this?

Aleena Umaiir
Contributor
July 10, 2024

This.PNG

Aleena Umaiir
Contributor
July 10, 2024

Here in the backlog , I have an item in 'To do' with 1d estimation, but it is showing 0. 

this is happening in only this project

Aleena Umaiir
Contributor
July 14, 2024

@Jack Brickey can you please help me in this? I am stuck here 

It should show the estimates of "To Do" items, it is showing me 0

 