Hi everyone
Is there a possibility to manage Sprints for several teams, when they working with separate jira-projects?
Scenario:
We have about 20 Scrum-Teams. They all should work with the same Sprint-Names and Dates. The Scrum-Teams would like to manage their own Versions and Components. Therefore, they need their own Jira-projects.
Is there a way to define the sprints, Start and close Sprints by a central role for defined Jira-Projects?
Thanks for your help and tipps.
Yes, we are doing this at the moment.. our approach is as follows:
- create a new issuetype "sprint marker"
- create a sprint mgmt project & agile scrum board, in which "sprint marker" issues are created
A project XXXXXX that follows the "company wide sprint" frequence, is typically defined as follows:
- consists of regular issue types (not sprint marker)
- agile board data is based on issues from the project itself + additionally includes sprint marker issues issues , e.g.
Issuetype = "Sprint Marker" OR project = "XXXXXX" AND issuetype in (Epic, Story, Analysis, Bug, "Test Issue") ORDER BY Rank ASC
- agile board gets a convenience quick filter, to hide the sprint markers on plan & scrum boards, e.g.
Issuetype != "Sprint Marker"
Next, you create future sprints:
Because the agile boards include the sprint marker issues, the sprints to which they are assigned will become visible in the planning mode view of the agile scrum boards & can be used to allocate the regular project work to.
The sprint marker issues are managed by our JIRA admin team & are closed at the end of the sprint, just before sprint completion.
Note that additional access rights on the 'sprint mgmt project' are required to complete/start sprints, so only limited users can still perform this.
Our various project mgrs take this into account & ensure required scrum activities are done by sprint completion & before the next sprint is started.
Cheers,
Ben
Hello Ben
That sounds very good and would also solve the problem, that the Sprints are shown in the Agil-Boards. I was quite sure, that the sprints are separatly in each jira-project.
I will go on to test your solution an i will reply at least on the end of the week.
Thanks a lot!
Roman
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Ben
I could already test this scenario on our staging-environment and it works perfectly. Thanks again for your detailed and complete description, it helped a lot!
Roman
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Roman,
Really glad this matches your requirements as well.
For us, this was important since our deliveries are timed to a predefined frequency.
This helps all teams to work towards the same time frame.
Cheers,
Ben
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Ben
Yes, thats also very important to us. We have over 20 ScrumTeams and all should follow the same sprint-time-scale as all results are deployed on the same time. Unfortunately the dependencies are very large.
We started with one Jira-Project and more and more teams wanted to work with Jira-Agile. That works pretty well. But now there are a few requests as described in the question.
Now i will have a look on othe questions and answers in this site. That could really help to organise the hole instance.
Thanks again,
Roman
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I guess ur already aware of SAFe? (we're not there yet, but working towards it)
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
What do you mean with SAFe?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Scaled Agile Framework ( http://scaledagileframework.com/)
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Ben
No, i was not aware of this. We are on the way to this. We changed our methodology on the beginning of this year to scrum, team by team. Now we are making our experiences on this way. Thanks for the tip.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Roman,
the thing is - sprint is attached to filter not to the project
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Sprints are actually global, and attached to issues, not filters.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
The Answer from Ben de Pauw confirmed this statement. I was not aware of this situation. Thanks for your help.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Atlassian Government Cloud has achieved FedRAMP Authorization at the Moderate level! Join our webinar to learn how you can accelerate mission success and move work forward faster in cloud, all while ensuring your critical data is secure.
Register NowOnline forums and learning are now in one easy-to-use experience.