I have a question about JIRA's version report:
According to the documentation, the predicted release date is based on the "estimated work remaining". When certain tickets have no estimation, does that mean that the prediction assumes there is no work associated with these tickets?
For example in our company not all stories are estimated right away and defects are (by design) never estimated. In order to estimate stories, we use story points.
And as for the items that you're never planning on estimating, you can set them to 0 instead of leaving them empty.
Hi Christoph,
The prediction does not assume there is no work associated with the unestimated issues, but as there is no estimate, it cannot take them into account for the prediction.
There is some information that might help you interpret the accuracy of the report:
A first thing - as also mentioned in the documentation your refer to - is the optimistic and pessimistic predicted release date. The prediction adds 10% of uncertainty / deviation to your velocity metric of past work delivered to account for fluctuations in the speed of delivery.
And second, there is an indication of the percentage of unestimated issues in your backlog (shown in red in the chart). Although they aren't quantified, it gives you an indication of the work in your backlog that is not accounted for in terms of estimations. So you at least get a feel of how reliable the predicted release date might be at a given point in time.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
@Walter Buggenhout what would be nice is if the same chart was provided but considered cycle time and used monte carlo instead of estimates - that would be REALLY powerful.
Why use a 10% for pessimistic and optimistic when you can use a monte carlo simulation? The chart would look the same, it would just have a confidence band with multiple "times to complete" with a % of certainty.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
@Walter Buggenhout It would make sense for the Un-estimated Issues to be given an assumed size (for charts and Sprint sizing) until actively sized.
This is essentially what happens now, just that the assumed ticket size is 0.
There just needs to be a question asked when a Project is opened:
"What size should be given to un-estimated issues (until they are estimated)?"
Options: 1,2,3,5,8,13... OR "Mean/Median/Mode of sized Issues"
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Also, if a story is linked to an epic that has been estimated, one could question if that story should be included in the "unestimated" work...
For example:
Epic A: 20 points
Story A.1: no points
Story A.2: no points
Well, until the stories get estimated themselves and then we remove the 20 points from the epic, they are still roughly estimated through the epic, no?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.