Hi Team,
Is their a way to Create Sub-task under Epic using Script Runner in Jira.
Please confirm over this if this is possible using Script Runner.
Regards,
Yash
Sub-tasks can't be direct children of Epics, assuming you have standard hierarchy. Sub-tasks are children of tasks/stories/bugs, which are children of Epics.
@Katie Nix is right. Jira has 'holy trinity/hierarchy' of three issue types.
Epic
v
Task/Bug/Story
v
Sub-task
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks Katie & Dave for the info.
One more thing to ask. This case scenario is not possible with anything, right. Not with Script Runner also, right?
Please confirm.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.