Using Jira Plans, we know that we can link two dependent Stories together.
We see that Jira will turn the linkage colour red if Story B is starting before Story A completes.
This is a finish-to-start linkage.
Is it possible to show a finish-to-finish linkage?
I.e. Story B can start whilst Story A is still going, but until Story A completes, Story B cannot complete.
The only way I can see to do this is via a workaround - i.e. split Story B into 2 pieces; link Story A to Story B(ii) and link Story A to the "very end" activity of Story B(ii).
I hope this makes sense!
Hi Brant. Thanks for the tag.
I still don't see that there is an answer; @Ravi Sagar _Sparxsys_ Ravi says " I don't think you can use AR dependencies to represent FF tasks."
Hopefully I am missing something?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
@Peter Norris sorry I should have looked that over more. I assumed that there is something that I did not know and it was possible. I should have looked a little closer. I am not aware of a way to do that in plans. You can use an App like BigPicture to represent that type of dependency.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.