Finish-to-finish linkage between work items

Peter Norris
Contributor
February 27, 2025

Using Jira Plans, we know that we can link two dependent Stories together.

We see that Jira will turn the linkage colour red if Story B is starting before Story A completes.

This is a finish-to-start linkage.

Is it possible to show a finish-to-finish linkage?

I.e. Story B can start whilst Story A is still going, but until Story A completes, Story B cannot complete.

The only way I can see to do this is via a workaround - i.e. split Story B into 2 pieces; link Story A to Story B(ii) and link Story A to the "very end" activity of Story B(ii).

I hope this makes sense!

1 answer

Peter Norris
Contributor
July 29, 2025

Hi Brant. Thanks for the tag.

I still don't see that there is an answer; @Ravi Sagar _Sparxsys_ Ravi says " I don't think you can use AR dependencies to represent FF tasks."

Hopefully I am missing something?

Brant Schroeder
Community Champion
July 29, 2025

@Peter Norris sorry I should have looked that over more.  I assumed that there is something that I did not know and it was possible.  I should have looked a little closer.  I am not aware of a way to do that in plans.  You can use an App like BigPicture to represent that type of dependency.  