I can't add a status and I am Jira admin, can you help?

Angela Williams September 11, 2018

I have just set up Jira for my team (a huge learning curve for me) but I can't seem to figure out how to add a status to my new column in my board

2 answers

1 accepted

0 votes
Answer accepted
Jack Brickey
Community Champion
September 11, 2018

@Angela Williams, welcome to the Community. The exact steps depend on a few things. First are you on Cloud or Server? If Cloud what project template did you use to create the project? While contemplating those questions try the following:

project > project settings > workflows

find your workflow and edit in diagram mode. Add a new status and the desired transitions or simply allow transitions from “all” other statuses. Save and publish the workflow. 

Now go back to your board and got to board settings, columns and add a column for your new status and map the status to that column. 

Angela Williams September 11, 2018

we are cloud and I believe I used SCRUM classic template

Jack Brickey
Community Champion
September 11, 2018

 Then the details I provided should work for you. give it a try and let me know. 

Angela Williams September 11, 2018

 I figured it out!, thanks for your help

Angela Williams September 11, 2018

s is possible to ask you a different question or do I need to start another topic?

Jack Brickey
Community Champion
September 11, 2018

 Generally best open a new question. However go ahead and ask here

Angela Williams September 11, 2018

Thanks! I have set our estimation to days , and want our burndown chart to reflect in days but it only shows hours.

Jack Brickey
Community Champion
September 11, 2018

Hmm, I have never seen it In days. I think it always will be an hours. Where did you set the estimation to days? If you are referring to entering in say Original estimate in days that gets converted to hours. 

Angela Williams September 11, 2018

ahh I see. that is what I chose for the burn down chart. we like to  to estimate in days rather hours and wanted the burndown to reflect in days

Jack Brickey
Community Champion
September 11, 2018

Unfortunately you can’t do this AFAIK. 

If my answers have helped please be sure to click the check mark as it helps other when searching. 

Angela Williams September 11, 2018

ok, thanks. sorry what does AFAIK mean?

Tzoe_Keat_Chiam September 12, 2018

AFAIK = As Fas As I Know :)

Jack Brickey
Community Champion
September 14, 2018

@Angela Williams, if the guidelines provided resolved your issue please consider selecting the checkmark next to the answer and vote button. However, if the issue was unrelated please share the actual issue/solution in a separate answer and select the checkmark there. This helps others in the future.

0 votes
Angela Williams September 14, 2018

Thank you