When I complete a sprint while there are still "in progress" tasks, I lose the view of that sprint and the associated tasks within that sprint in the backlog view. I can eventually find the issues by going into the issues area but I was hoping that I could somehow see the tasks that were left in each sprint bucket and then just move them into the next sprint. Is there a way to do this?
Hello @Kristine Gemici
From the Reports section of the agile board you can review the sprint Burndown Report to see all the issues that were in the sprint, which includes a section for incomplete issues.
Also, when you click the Complete Sprint button you should be getting a pop-up that tells you how many issues where completed and how many issues are incomplete, including an option to move the incomplete issues to the backlog, a new sprint, or an existing sprint.
Hi @Kristine Gemici - I agree with what @Trudy Claspill said.
The reason you are given a choice as to what to do with the incomplete issues is because in Scrum - in theory - each Sprint should/could have a new and different Sprint goal, which needs a possibly different set of issues to achieve. Jira then gives you a choice of whether to return the incomplete issues to the Backlog for consideration in a later Sprint, or to just designate them to another Sprint (such as the next Sprint) when Completing the current Sprint.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks so very much Trudy & John!! That is what I needed to know! Greatly appreciated!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.