We've updated our Epic workflow to change the Epic status with a post function. So when the Epic workflow status is changed the "Epic Status" is changed accordingly.
The following KB article describes how to do this: https://confluence.atlassian.com/jirakb/linking-epic-status-to-the-epic-issue-status-881516333.html
There is one question left. How to keep Epic status and Epic workflow status in sync when Epic status is changed from the Scrum board (Using "Mark as Done")
We would like to set the issue workflow status to Done when "Mark as Done" is selected from the Scrum board. Is this possible? Or isn't it a good idea at all?
Hi @Ron Becker
It's not as simple as post-functions and workflow properties only apply to workflow statuses, not the Epic Status.
You'll be able to create this behaviour with an application - such as:
Personally, I would consider if this is necessary. For our users, we find it more likely they'll transition an Epic to Done via the workflow than via Epic Status.
If we're concerned they'll miss Epic transitions or want them to track more closely we'll:
Ste
Thanks for your answer. Valuestreams which are concerned that Epic Status and Epic workflow status are not alligned can use a dashboard or filter to check consistency.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Atlassian Government Cloud has achieved FedRAMP Authorization at the Moderate level! Join our webinar to learn how you can accelerate mission success and move work forward faster in cloud, all while ensuring your critical data is secure.
Register NowOnline forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.