Next-Gen Jira - Parallel Sprints Not Working?

Victor Burgos
Contributor
May 30, 2019

Can't seem to figure it out. Should be simple, have it checked off in Jira Software configuration but can't seem to start a new sprint. 

1 answer

1 vote
Scott Theus
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
May 30, 2019

Hi @Victor Burgos

Parallel sprints are not available in next-gen projects yet. There is an open request to add them, you can review and vote on it here: JSWCLOUD-17195

-Scott

Victor Burgos
Contributor
May 30, 2019

Sigh. Thanks. No reason why they are gimping Next-Gen so hard.