Non working days display by default on the time-sheet gadget and burndown chart. Why?

Amy Tidwell August 14, 2019

Is there anyway to remove non working days from these charts?  

1 answer

0 votes
Olga Videc
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
August 14, 2019

Hello @Amy Tidwell 

https://confluence.atlassian.com/jirasoftwarecloud/configuring-working-days-764478050.html

Referring to this documentation for Burndown Chart

Configuring nonworking days

Go to your board, then select more -> Board settings


Click the Working day's tab
If your team has a different time zone from that of the server, select the team's time zone


In Standard Working Days, select all the weekdays during which your team typically works.

In Non-Working Days, click Add Date to specify holidays or one-off dates during which your team will not be working

To remove a non-working day, click the x next to the date


These settings will be reflected in the following reports and gadgets:

  •  Burndown ChartSprint ReportEpic ReportVersion ReportControl Chart
  • Sprint Health GadgetBurndown Gadget

For Time sheet

You are using a gadget? It's not a standard gadget, does it come from this add on

BR, Olga

Senthilkumar
Contributor
December 23, 2019

Hi,

If i dint select Saturday and Sunday in the Board setting under Standard working days, it means, that those days wont reflect on the reports right?