Hi community,

I'm trying to use plan to track stories from different sprint in the plan. 

Firstly, issue hierarchy is initiative--> Epic --> story. Initiative and Epic are in the same project. But stories are in another project. I use a JQL "

issue in portfolioChildIssuesOf("PPMD-2")

" where PPMD-2 is my initiative as a filter to create a scrum board. And I create a plan based on this scrum board. In the view setting, I choose to group issues by sprint. My goal is to show sprints on the timeline. But I don't know why it's not working. 

Below is the screenshot. 

spint capacity view.PNG

1 answer

1 accepted

0 votes
Answer accepted
Dexter de Vera
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
April 8, 2024

Hi @Yi Meng ,

It only works if you have team assigned in issues and the team is added in plan

team in plan set to:

issue source = board should be a scrum

planning style = Scrum.

 image.png

Then view settings - group by sprint - check show capacity on timeline

 

Yi Meng
Contributor
April 9, 2024

Thanks @Dexter de Vera 

It works when I change view setting to group by team and check 'show capacity in timeline'. 

I think it would be nice if Atlassian can make it possible to show sprints on timeline without team assigned to stories. 

Thanks for your help. 