Hi
In Jira we have 3 project
Project A contains the stories requested for the business
Project B and C contains the stories from team 1 and team 2 to realizes the stories of project A, so Project A story 1: Project B story 1 + Project C story 1
If Project B story 1 = story point 5 and
Project C story 1 = story point 4
then Project A : story 1 = story point 9
Now I have to calculate the story points of Project A manually but I'd like to have that manually in Jira. Is this possible?
P.S. I'm using Jira Software Cloud and Portfolio for JIra
Thanks in advance
Luciana
It is not possible at the moment
Is it possible to have the "story" in project A be an epic? That way you'd get the summary done automatically.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
No :( they should be story. Thanks for the answer
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
How do you get the "summary done automatically"? We point our task and I need a way to show the sum of all story points for a single epic. Seems like this would be a basic feature.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.