Hi, I have a really simple project
a workflow of 3 (To do, In progress and Done)
I have no filters
I was using it fine yesterday, creating epics and tasks using the top create button and tasks were showing on the board
Today however something has changed, I created a new epic and it was added to backlog but not the board
I created a new task and again it was not added to the board.
When I create both a task and epci i get this message: "For issue SF-62 to be visible, it must match your project and filters, and have a status that’s assigned to the board."
However it is in the project, I have no filters at all and the status is the standard out of the box To Do (and the kanban board is the standard out of the box kanban board.
Very frustrating
I've uploaded screen grab of project board if that helps
Hello @Richard Grinter
Welcome to the Atlassian community.
I see that you are working with a Team Managed project, with a Kanban board and you have the Backlog feature enabled.
Have you checked the Backlog screen to see if the issues are displayed there?
Additionally, view one of the new issues and check the status to which it is set. What is that status? Next click on the three dots button in the upper right corner and select Configure Board. The click on the Columns option. Confirm that all statuses are mapped to a column and none are in the Unmapped Statuses area.
Hi @Trudy Claspill Trudy, thanks for the response.
The issues do show in the backlog
The status is To do (set by default by jira)
I only have To do, In progress and Done as statuses
I've been into the board settings and there are no unmapped statuses
It is really frustrating that it was all working perfectly yesterday. There are only a handful of users to the project
I really appreciate your help with this
Richard
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
When I am viewing the Kanban Board of a Team Managed project, and the Backlog feature is enabled, and I click the blue Create button, then the new issues I create are automatically put in the Backlog rather than on the board.
However if I instead use the +Create Issue button at the bottom of the To Do column, then the issue is added directly to the board.
I can't really say if it worked differently yesterday because I don't work with Team Managed projects every day. But I think this is how it has been working.
If you don't have the Backlog feature enabled, then the issues would automatically display on the board regardless of how you create them.
Did you newly enable the Backlog feature since yesterday?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hmm, it might be that one of my team members did enable backlog yesterday
ah I have now spotted the add to board option in the backlog.
thanks for your help, it doesn't work exactly how i'd like but i think i know what to do now, I appreciate you taking the time.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Forgive me for not pointing out the option on the Backlog screen to add issues from the backlog onto the board. I erroneously assumed you were familiar with the Backlog screen functionality.
You can right-click on an issue and select the Move To option and select Board to move an issue from the Backlog to the Board. You can also drag and drop the issue from the Backlog list section to the Board list section above it.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi @Richard Grinter ,
=> @Trudy Claspill has mentioned clearly about the Backlog and board configurations.
=> @Richard Grinter Here you can start the sprint in Team managed project then only the Issues will be displayed in the Board.
=> Kindly check from your end that sprint has started and check the Issues will be added to the board or not.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
The post states that the board is a Kanban board, not a Scrum board.
Sprints are only applicable in a Scrum board.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks for your clarification.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.