When planning a sprint I want to plan with the remaining story points of all stories that are combined into a sprint that is about to start.
When finishing a sprint I want to see the story points initially estimated to get an idea of the work that was completed.
Is this possible? Currently in the backlog view, remaining story points is displayed per story. This is also true for "story points", but only a total of "story points" is calculated.
@Arjen Verweij, it would seem that what you want is certainly possible. When planning/forming the sprint the story points are visible. Once you start the sprint and at the end you can monitor via the Sprint Burndown report.
When I have the backlog view in my setup of JIRA, I certainly don't have a total of remaining story points of the stories that are about to be put in a sprint. Only total of the initial story points.
This issue is about work carrying over from a previous sprint, so we can still do planning based on velocity.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Have you found a solution to decreasing the story points of tickets carrying over from previous sprints, i.e. enter "remaining story points" while planning the sprint to ensure proper velocity tracking?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.