Unable to start Parallel sprint on a Software project(moved tickets from Next Gen project)

Rajesh Konda
Contributor
February 7, 2022

Hi All,

As parallel sprint doesn't works for Next Gen projects, Moved all next gen tickets to a new software project and tried to start sprint but an error is thrown as 
We couldn't start this sprint because it belongs to the next-gen project CLOPS board which already has a sprint in progress. Next-gen projects do not currently support parallel sprints. Can any one help me please to sort out issue.

2 answers

1 vote
Pramodh M
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
February 7, 2022

Hi @Rajesh Konda 

It may be possible that issues that you have moved have the sprint value which is created in team managed project!!

Can you also change the sprint value for the issues to match the new sprint created in a company managed project and surely it will then work.

Thanks,
Pramodh

Rajesh Konda
Contributor
February 8, 2022

Hi @Pramodh M  Thanks for the response, yes i thought same and changed sprint value and created a new unique sprint and moved all tickets under new sprint. Then clicked on start sprint same error shown. Don't know May be few tickets have closed sprint names in dropdown of tickets, will that could cause issue?

Pramodh M
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
February 8, 2022

@Rajesh Konda 

Please note an issue can be present in only one sprint at the moment,

And for parallel sprint to work it should be of company managed project board

can you include the screenshot of error you are getting!!

0 votes
RISHAV KUMAR GUPTA
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
February 7, 2022 edited

Hi @Rajesh Konda As said correctly team managed projects doesn't support parallel sprints .

As per your query , I tried to move the issue that's been started in sprint in scrum  next gen proj to scrum company managed project . it was working fine . when the ticket is moved it will be shown in the started sprint section and you can edit the date . && there were no error .

When you are doing bulk move try to map it correctly otherwise it might show error. 

This might help .

Thanks ,

 Rishav 

Rajesh Konda
Contributor
February 7, 2022

Hi @RISHAV KUMAR GUPTA  Thanks for the response, 

In my Next-Gen project currently one sprint is running, have taken few of future sprint tickets and moved them to a scrum company managed project and tried starting sprint on new project the above error is thrown, thought issue could be with sprint name as i used same name on both projects.    

Then i editing Sprint name and again tried to start sprint but no luck again same issue occurred.

Moved one ticket to new status, During bulk operation i have mapped all types and project correctly, cross checked again all were moved properly but same error.

.

RISHAV KUMAR GUPTA
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
February 8, 2022

Hi @Rajesh Konda disable the multiple sprint option in the product section . then try it might work .

parallel sprint.png

thanks ,

Rishav

Rajesh Konda
Contributor
February 8, 2022

@RISHAV KUMAR GUPTA, thank you. I'm not sure how it started, but I tried a few minutes ago. The sprint began without any modifications.

 

Thank you both for your assistance, I greatly appreciate it.

Suggest an answer

Log in or Sign up to answer
TAGS
atlassian, loom, AI, meeting recording, community