I love the new Next Gen version of the Roadmap to view timelines and the full rollup of Epics, but is there a way to view the timelines for the Issues and/or Tasks within the Roadmap as well? View of the sum of the whole rather than just the high level. Is there a way to do this within a dashboard as a workaround if not on the Roadmap? Thanks!
Hello @Kelsie Ross
Unfortunately, the Next Gen Roadmap does not display the timeline for issues underneath Epics.
To see this level of detail you would need to use Portfolio for Jira though there are documented limitations when using Portfolio for Jira and Next Gen projects.
Parent-child relationship: If you try to save a story to epic relationship in Portfolio, it won’t be properly stored in next-gen.
Sprints: Portfolio doesn’t load sprints coming from next-gen boards.
Assigning issues from Portfolio won’t work in next-gen boards.
Story point estimates: You won’t be able to commit story point estimates to Jira if you’re issues are next-gen.
Time tracking: You can still set time estimates in Portfolio but they won’t show in Jira.
Issue type mapping: You next-gen project issue type will all implicitly be mapped to the story hierarchy level unless you fix that in the Portfolio hierarchy configuration.
Target dates: You can use target dates in Portfolio, however, if you commit them to Jira, the changes won’t be reflected in your next-gen roadmap.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Same here! Thank you!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Also requested by my group
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I totally agree...it's urgently needed!
To have all stories or task starting with the EPIC startdate, independant from the stories' or tasks' actuall dates (as it semms to me until now), doesn't make any sense.
At least the display of the correct beginning would help a lot.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
update?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks for your feedback everyone.
Please vote on the suggestion here https://jira.atlassian.com/browse/JSWCLOUD-18668
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Same here, we also need this feature. Thank you!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello All,
I can confirm this feature has now been rolled out for all Team-managed projects and is an option within the project settings. Enable Roadmaps as a feature, and if not previously done so, please enable Child level issue scheduling. This can be found under Project Settings > Board > Roadmap.
More info below:
This feature is not enabled by default on each project, but it’s easy to turn on (if you have project permissions). Learn how to enable child-level planning for kanban teams. The roadmap uses the fields "Start date" and "Due date" to reflect the timeline bar schedule.
For scrum teams, child issues are scheduled according to the sprint to which they’re assigned. On your roadmap, the schedule bar for all child issues is the same size regardless of their estimated duration, aligning with the sprints at the top header of the roadmap. You will need to have sprints created with dates to see them on the roadmap. https://support.atlassian.com/jira-software-cloud/docs/schedule-work-for-scrum-teams-on-your-roadmap/
Happy planning everyone.
Danny
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks Danny but its not exactly what is being requested.
"... using the the dates of the sprint to which they're assigned"
So it does not, when enabled, show the start/finish dates/timeline for individual tasks.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
It's a shame that no one from the Atlassian team seems to feel responsible for any answer regarding an update...
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi @Robin Berger and @Sveni you can vote on the suggestion here https://jira.atlassian.com/browse/JSWCLOUD-18668
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Same issue during evaluation process, this is really needed, basic and would just kill the PM activity from this tool very quickly...
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Jira is traditionally for Agile development, not waterfall.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
after all this time they should by now realise you don't want to just see the timeline for an epic
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I recommand you use "multi-sprint" (admin shuld allow this feature)
It is not convenient to use but useful
1) https://{your account}.atlassian.net/jira/settings/products/jira-software-configuration
=> multi-sprint? set "on"
2) https://{your account}.atlassian.net/jira/software/projects/PXVL/settings/features
=> backlog and sprint set "on"
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.