Hello togehter,
when I add multiple dependencies to a, for example task, because this task is going into multiple milestones, the end date will be set to latest milestone instead of the earliest milestone.
In Microsoft project I could choose from where it should be calculated. In WBS I didn't found such an option.
Is there a option that I missed or is it still not working.
best regards
Tom
Hello @Tom Richter
Thank you for bringing this behavior to our attention and creating this Community Question.
WBS Gantt-Chart was designed to use the last end date by design and for now, it was designed this way so it can auto-calculate when the end date of the parent issues and the project.
We are looking forward to hearing more from you. If you need assistance with our plugins or have any other questions, please, contact us anytime at Ricksoft-Support.atlassian.net. We'll be happy to help.
We wish you a great day!
Kind Regards,
Alessandro C. | Support Engineer
Ricksoft Support Team
Hello @Alessandro Portela Cristiano
Thank you for your answer.
Hopefully there will be an option in the future. Currently this means for me that I can not use this plugin for planning my activities or need to think about a workaround.
Best Regards,
Tom
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks for your feedback, @Tom Richter
If you would like to, we will be more than happy to hear about your use case and why this is actually a deal breaker for you.
We have a roadmap in the Productboard platform where you can leave your feedback by using the Submit Idea button: https://portal.productboard.com/ricksoft-inc/5-wbs-gantt-chart-for-jira-cloud/tabs/10-under-consideration
If you still would like to try WBS Gantt-Chart, one thing you can do is to enable the Manual Scheduling for the parent issues by by adding "Manual" column and switching it on. Then, you can update their Finish Dates by using Jira Cloud Automation.
This could be done by triggering an update in the Parent issue whenever there a child Finish Date field is updated. If you need assistance doing that, please do contact us and we can guide you through that process!
Kind Regards,
Alessandro C. | Support Engineer
Ricksoft Support Team
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi @Alessandro Portela Cristiano
I created a Idea at your portal. :)
Jira Cloud Automation is not that easy possible to use, because we are working on a customer system. But I will hold it in my mind as a possible solution.
Best regards
Tom
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello @Tom Richter
Really appreciate your feedback!
If there is anything else you would like to ask, let us know. We will be more than happy to assist!
Kind Regards,
Alessandro C. | Support Engineer
Ricksoft Support Team
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.