Why can't I manually schedule one item in structure gantt?

Lisa de Araujo August 20, 2021

I have one item in my Structure Gantt that does not allow me to manually schedule it. It is set up the same as the others. I can't figure out what is different about it2021-08-20 13_29_22-Context Initiatives _ Gantt Chart - Structure - OA Jira.png

All the others look like this:


2021-08-20 13_47_27-Context Initiatives _ Gantt Chart - Structure - OA Jira.png

1 answer

1 accepted

1 vote
Answer accepted
alexeypegov
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 20, 2021

Hello Lisa!

This is Alexey from ALM Works.

The item you've mentioned is a Group, and not a regular Task or Milestone: Groups looks like square brackets. Group schedule (including start and duration) is determined by the group content, i.e. tasks and milestones that are part of this group. It is currently impossible to control group position anyhow except with adjusting position of its child elements (group's children are determined by WBS hierarchy).

In our backlog, there is an improvement related to ability to define group constraints. As soon as it is implemented, it should be possible to control groups position more flexible way.

Best regards,

Alexey

Lisa de Araujo August 20, 2021

The text in the square brackets are just a part of the title - it's not a group - it's an initiative issue type like all the others with Feature child issues. I've not set up any groups at all. 

I don't know what you mean by WBS?

Lisa de Araujo August 20, 2021

Nevertheless, I just removed it and re-added it and now it seems like I can manually schedule it. 

Thanks.

alexeypegov
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
August 20, 2021

Hello Lisa,

Sorry for the confusion, I didn't meant "text in square brackets", but that element that "looks like a square bracket" (similar to the one arrow points at):

Screenshot 2021-08-20 at 18.47.49.png

Please, see our docs, describing different element types.

By WBS I mean Work Breakdown Structure -- the task hierarchy visible in the left panel (opposite to the Gantt chart itself).

Best regards,

Alexey.

Like Dave Rosenlund _Trundl_ likes this