laudren_florent January 18, 2019 edited

I have edited time tracking format but still estimate time of issues are displayed in standard Jira format.

I'd like to have estimate time and ellapse time displayed in days, not weeks+days.

 Clipboard01.jpg

Clipboard01.jpg Clipboard02.jpg

 

 

 

1 answer

1 accepted

0 votes
Answer accepted
Petter Gonçalves
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
January 18, 2019

Hello Laudren,

Thank you for your feedback about this behavior.

In fact, we've already identified that the only time format available for Time tracking in the New Issue View of JIRA is Weeks/days/hours. That's why we reported this behavior as a bug to our development team:

New issue detail view won't display the Time estimate in hours

Please, watch the bug to be notified about the progress of its fix implementation.

For now, we recommend you to keep using the old Classic View of JIRA to keep displaying the time tracking in the format you want.

Let us know if you still have any questions.

laudren_florent January 18, 2019

Unfortunally, it is an Entreprise project so the 'old' vue is not a solution

Suggest an answer

Log in or Sign up to answer
TAGS
atlassian, likes for trees, atlassian community, social impact, tree planting campaign, community kudos, atlassian giving, environmental impact, sustainability, likes for good, atlassian social responsibility, community challenge

Make every click count—help us plant 50,000 trees! 🌳

Want to make your everyday Community actions directly contribute to reforestation? The Atlassian Community can achieve this goal by liking a post, attending an ACE, sending your peers kudos, and so much more!

Help us plant more trees
AUG Leaders

Atlassian Community Events