Regarding the Sprint

kA
Contributor
November 25, 2013

Hi friends,

I have 30 issues in backlog and i take the 15 issues in sprint-1. Before the sprint expired I have done only the 10 issue from that. The remaining 5 issues can't done by me before the sprint expired. Now i check that remaining 5 issues, i can't able to found in backlog.Where i can found the remaining issues.

please share your thoughts,

Thanks in advance,

Karthik A.

3 answers

1 accepted

0 votes
Answer accepted
V
Contributor
November 25, 2013

Have you Closed the Sprint by clicking on the Complete Sprint button under Work mode of the board? If so, you should see the issues at the top of the backlog

0 votes
kA
Contributor
December 1, 2013

Hi venkat,

I could not perform any changes to the board filter.

Thanks,

Karthik A.

0 votes
kA
Contributor
November 25, 2013

Hi venkat,

Thanks for your updates, In my case the Sprint Time line was overed then only the sprint was completed. so i could not able to find remaining issues. In backlog i could not find it. Where i can get the remaining issues.

Thanks,

Karthik A.

V
Contributor
November 25, 2013

Have you made any changes to the board filter after sprint completion?

Suggest an answer

Log in or Sign up to answer
TAGS
atlassian, loom, loom for training, loom for teaching, video training, async learning, online education, screen recording, loom tutorials, loom use cases, atlassian learning, team training tools, instructional video, virtual training tools

🛗 Elevate Your Training and Enablement with Loom

Join us June 26, 11am PT for a webinar with Atlassian Champion Robert Hean & Loom’s Brittany Soinski. Hear tips, stories, and get your burning questions answered. Learn how Loom makes training and enablement easier. Don’t miss it!

Register today
AUG Leaders

Atlassian Community Events