I am trying to get our estimates shown in the backlog.
I have followed this https://confluence.atlassian.com/jirasoftwarecloud/configuring-estimation-and-tracking-764478030.html but I still can't get it to work.
I have created a test task, and get the "Time estimate" field here, but it is not available when creating a new task - only the estimate field (which is not shown i backlog)
How do I get "time estimate" to be a part of the create task and edit task view?
Hi @Maja Aagaard,
You should have by now enabled your board configurations to use appropriate option in Estimate tab
Please note that the create issue screen has Original Estimate field only.
If you need further inputs on this then please provide
Regards,
Ravi Varma
Hi @Maja Aagaard,
Have you added the Time Tracking field to the Create and Edit screens of your Task Screen Scheme?
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Glad I could help :)
@Ravi Varma is also correct, I would verify your Estimation configuration located within the Board Settings.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Manage Confluence like never before! This new learning path teaches you how to manage content, users, and permissions while optimizing user experience. Built for admins at all levels who want to confidently lead and unlock more innovative collaboration.
Learn more
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.