I have a scrum board, and I'm using story points as the burndown metric. At the beginning of each sprint, we break down issues into subtasks/hours. What I'd like to be able to do is sum up the number of hours for all of the issues in the sprint. I don't need a burndown chart for this, but I just want to make sure we haven't committed to way more hours than are in the sprint. Is this possible?
i think your answer is already there. We do the same -- story points for stories and hours for tasks. while you're planning a new sprint (and before you've clicked "Start Sprint"), you'll see something like the below. the "remaining" shows the number of hours in the sprint while the "estimate" shows the number of story points. if you don't see what i'm seeing, considering upgrading. it might have been added in a future release.
Tanner, thanks for the reply. I only see that though if I set the Time Tracking (under project Configuration > Estimation) to Remaining Hours. The problem with this is that it makes the burndown chart show up in hours as well. Do you have a burndown chart in points (I have my estimation statistic set to points)?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
here's a quick run down of our process:
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks, that's similar to what we do as well. I was just trying to get a sprint burdown chart in points instead of hours, while still being able to show the number of hours that we've committed to. It looks like they may be linked.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
instead of a burn down chart in points, consider using the new agile widget that comes with one of the new version of JIRA agile. it looks like so, and will show you how things are progressing as far as points go while still having a burn down chart in hours.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
This was very helpful since I had the same questions as Jeff. Thanks Tanner!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I see this thread hasn't been touched in a while, but I don't feel it's been really answered. I'd like to achieve in Jira what Rally/Agile Central does. Blue bars are hours left to do on tasks. Green bars are accepted stories/points. Any Jira wizards who want to take a crack at this?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I'm looking for a burndown chart like yours, were you able to get it to work?
-Scott
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.