We have issue in getting sprint reports. Let me explain it in an example:
on Sprint #1:
on Sprint #2:
Hope you to understand our problem and happy to read your solutions or guidance.
Thank you.
We use JIRA 7.12 server version.
I believe the problem you are having is that JIRA is not designed to have incomplete work carried across sprints.
Work should be planned to be closed within a single sprint. (Agile/Scrum framework)
This would explain why the same story, being tagged with two subsequent sprints, has a total time of 3 days (for both sprints).
If the story had continued into a 3rd sprint, then 3 sprints would reflect the total time spent (effectively tripling the total time spent).
Conclusion: Ensure work is planned and completed in one sprint (i.e. no carry-over).
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.