Hi,
We've been running multiple projects for multiple "project teams" all under one large project umbrella. We've discovered that epics are a nice way to link that work across project teams together, but several issues have come up as a result. Epics themselves live in yet a third project, for management and prioritization. I'm hoping someone here can help us sort out what we need to do.
Is it possible that these are addressed in a later version?
BTW, we're running version 4.4.1 of GreenHopper, and 4.1.1 of JIRA.
Thanks,
Paul
This is the only way I have been able to roll up status of an Epic across multiple projects. Perhaps it will be useful to you.
Obviously, you will need create/view/edit privileges in all 3 projects.
The trick, here, is that you must maintain the hierarchical relationship between the Epic and its children. If Projects B and C "Move" their User Stories to Epics the parent-child relationship is lost.
If anyone has found a different method that works I would love to hear about it.
Have a great day!
Ed
I have similar requirement as you have...Paul . I have an Epic with several related Issues across different Projects. Can Epic duration be viewed as sum of 'related' Issues duration? Please note that Issues under an Epic are not necessarily sub-tasks under the same Epic. Instead Issues are spread across projects and are linked to Epic. I am using JIRA + Agile +Gantt Chart plugin. Any ideas as to how to resolve this?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I have similar requirement as Paul has. I have an Epic with several related Issues across different Projects. Can Epic duration be viewed as sum of 'related' Issues duration? Please note that Issues under an Epic are not necessarily sub-tasks under the same Epic. Instead Issues are spread across projects and are linked to Epic. I am using JIRA + Agile +Gantt Chart plugin.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
I have a suggestion for this question:
https://answers.atlassian.com/questions/87277/epics-beget-stories-and-stories-beget-subtasks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Paul,
You would need to upgrade to at least JIRA 4.4.3 and GreenHopper 5.8 in order to use the Rapid Boards. That's when they were first made available.
If you are going to upgrade, I'd probably recommend moving to JIRA 5.1 and GH 6 though after testing new features in your environment. Lots of improvements across the board in both.
I would check out what's new in GreenHopper and JIRA 5.1 for more.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks Adam.
Yes, we want to upgrade. It just turns out that the upgrade is likely non-trivial for us, spinning up into another large project that doesn't really get the answer for us immediately. Thanks though. I have access to another JIRA instance that is on 5.1 (hosted) that I can experient with. I'll have a look at rapid boards there as proof-of-concept.
Cheers, Paul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Understood. Good luck.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Greenhopper's Rapid board is able to work on a few projects at the same time.
You may try to set up rapid board for multiple projects and have Burndown statistics for epics.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks Matt,
I'll look into it... but unfortunately the version we're running doesn't have a rapid board.
Thanks, Paul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.