Hi,
I am unable to create a Task under Story. Only Subtask is possible but I have a need to have Story->Task->Subtask.
Please check/suggest
Regards
Asha
Welcome to the Atlassian Community!
Yes, this is correct, the hierarchy is Epic -> Story (or task, or any other name you want) -> Sub-task.
Sub-tasks of sub-tasks is an anti-pattern, it just makes a completely unusable mess in most cases. The best case is that it drags you into massive micro-management, which is completely unproduvtive.
You should be looking at your processes, trying to make them into a function shape that uses Epic -> Story -> Sub-task as intended. And probably look upwards above epic.
Hi Asha,
What kind of problem you are trying to solve? There must be another way to solve the situation.
Regards, Mindaugas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.