WBS Gantt-Chart milestone date not updated when finish to start issues are changed

Sérgio Nogueira December 19, 2023

Hi, when using WBS Gantt-Chart we saw that the millstone date is not changed after the predecessor issue end dates is changed. The milestone depends on another issue in a finish-to-start relation.

Did anyone had this same issue?

Thanks

1 answer

0 votes
Kinay Mizuho December 20, 2023

Hi Sérgio Nogueira,

In WBS Gantt-Chart for Jira, once you convert to milestone, the start/finish date is fixed. It doesn't matter if it has predecessor issue.

To change the start/finish date of the milestone, please convert to regular task and move the predecessor issue. It should change the start/finish date.

 Milestone.gifthe start/finish date accordingly.