Hi, when using WBS Gantt-Chart we saw that the millstone date is not changed after the predecessor issue end dates is changed. The milestone depends on another issue in a finish-to-start relation.
Did anyone had this same issue?
Thanks
In WBS Gantt-Chart for Jira, once you convert to milestone, the start/finish date is fixed. It doesn't matter if it has predecessor issue.
To change the start/finish date of the milestone, please convert to regular task and move the predecessor issue. It should change the start/finish date.
the start/finish date accordingly.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.