Why can't I set default working hours as 7.5 per day?

Tom Cowles
Contributor
January 30, 2018

I've tried several times to edit the time tracking default hours per day from 7 to 7.5. It allows me to make the change, then shows up as having saved as 7.5. However, when I navigate away to another screen, then navigate back, this has reset to 7 hours again.

 

What gives?

7 answers

1 vote
Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
October 11, 2018

Ok, I found it.  We're both right, sort of.

Jira Server supports partial hours (I now have a working day 3.14 hours long as I tried to test it with π and it only let me have two digits)

This function has been removed from Cloud, and it now silently rounds up to the nearest integer hour without telling you.

Seems like someone has downgraded Cloud for no apparent reason - I can't see an issue or blog explaining why it's been done.

Ilze Schoeman
Contributor
October 11, 2018

I'd guess this is a bug, not a downgrade. I will raise this with their support desk.

Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
October 11, 2018

With Cloud breaking so many things now, I'm lost on whether to call something a bug or a downgrade!

Ilze Schoeman
Contributor
October 11, 2018

I've raised it with the service desk for anyone interested in following this. 

https://getsupport.atlassian.com/servicedesk/customer/portal/23/JST-424874?_ga=2.41883234.111631883.1538996631-1366096534.1538569729&_gac=1.204785956.1538742994.EAIaIQobChMIrpLIqajv3QIVCLXtCh1zXwHHEAAYASAAEgKwL_D_BwE

 

I am confident they will fix this, as having it as it is will make all the reporting data incorrect in regards to resources and their capacity!

miikhy
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
October 11, 2018

Thanks @Nic Brough -Adaptavist-, completely agree with you...

We'll see if @Ilze Schoeman can share any feedback from Support Team (as your ticket is private by default).

Cheers

1 vote
Ilze Schoeman
Contributor
October 11, 2018

I agree... this is not resolved.. It does not work

 

As far as I can see I am unable to set a working day to a decimal place - 7.5 hours... 

 

Please see my screenshots @Nic Brough -Adaptavist- please HELP 

 

Screen Shot 2018-10-10 at 15.58.22.pngScreen Shot 2018-10-10 at 15.58.28.pngScreen Shot 2018-10-10 at 15.58.35.pngScreen Shot 2018-10-10 at 16.22.19.png

Ilze Schoeman
Contributor
October 11, 2018

@miikhy if you could assist with the above that would be amazing! 

1 vote
miikhy
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
January 30, 2018

Hi Tom,

Could you please confirm you have deactivated time tracking, changed the value to 7.5 and re-enabled time tracking? Just tried it here and it's working well!

Cheers

Tom Cowles
Contributor
January 30, 2018

Hi Micky

When I click 'disable time tracking' all fields disappear and there's no option to edit anything, only the option of re-enabling time tracking - I get this message:

 

"Time tracking is currently disabled for all projects. To access time tracking options and log work in issues enable time tracking above."

 

I've tried logging 7.5 hours under a task, and it is showing as '1 day', but I've a feeling this is just rounding down.

 

Cheers,

Tom

 

 

Nic Brough -Adaptavist-
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
January 30, 2018

That implies your change has worked - Jira would display 7h 30m if your day was still set to 8h

Tom Cowles
Contributor
January 31, 2018
Originally it was set to 7h, so I suppose it would say 1d 30mins? Either way I'll assume it has, thanks for your help.
Lars Sundstrom July 4, 2018

Also if you edit working hours under issues timetracking it does NOT show/allow 7.5 it sets it to 7 so the edit field needs to be changed to support decimals and actually show them. 

0 votes
Mihai Schwarz
Rising Star
Rising Star
Rising Stars are recognized for providing high-quality answers to other users. Rising Stars receive a certificate of achievement and are on the path to becoming Community Leaders.
April 26, 2022

Has anyone solved this mystery? :) I encounter the same issue...

0 votes
Ilze Schoeman
Contributor
October 12, 2018

Yes - I can confirm this is a UI issue, but the settings are in fact correct. 

I set the time tracking to be 7.5 hours in a day - save. 

Created a task - estimate: 1d

Logged time - 30mins

Remaining estimate - 7 hours

 

Please see my screenshot. Screenshot 2018-10-12 at 10.33.51.png

0 votes
Lars Sundstrom October 11, 2018

Folks,

raised this before. It is stored and calculated as 7.5 AND Atlassian is to lazy to change the display setting.  The current setting does not show decimals. It seems to me to be trivial to change it to show 2 decimals...but Noooooooo that would be way to sensible.....

0 votes
Tom Cowles
Contributor
October 11, 2018

Yep on reflection it indeed doesn't work. I set as 7.5, the change appears to stick, then shows as 7 again when reloading the page