incorrect Remaining estimate

Artem Shukman
Contributor
March 12, 2025 edited

Hi team!

i think i found a bug.

How to reproduce:

1. Create task witn any standart type

2. Set  time track 1h.

3. set original estimate 1d

4. set time track 1h and look to field remaining estimate.

There is "0m"... Why?

If you want to collect reports on this field, tasks with this incorrect estimate will not be included to reports and its note good.

Will you fix this?

2 answers

1 vote
Karan Sachdev
Atlassian Team
Atlassian Team members are employees working across the company in a wide variety of roles.
March 12, 2025

Hey Artem,

 

With the current product design, it is expected to add the Original Estimate only once, before any time is logged. For detailed explanation on this, please review the explanation shared by the product manager on this suggestion ticket: https://jira.atlassian.com/browse/JRACLOUD-77064

Thanks!

0 votes
Artem Shukman
Contributor
March 12, 2025

For now, there is only one solution - to put the original estimate first. But this is not always possible right away..

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
STANDARD
TAGS
atlassian, atlassian government cloud, fedramp, webinar, register for webinar, atlassian cloud webinar, fedramp moderate offering, work faster with cloud

Unlocking the future with Atlassian Government Cloud ☁️

Atlassian Government Cloud has achieved FedRAMP Authorization at the Moderate level! Join our webinar to learn how you can accelerate mission success and move work forward faster in cloud, all while ensuring your critical data is secure.

Register Now
AUG Leaders

Atlassian Community Events