I moved all the issues from Project A to Project B. All of the standard issues moved fine but the sub tasks did not move. Now I have issues in Project B and their sub tasks in project B. How do I make the sub-tasks to move to project A? It is become really difficult to track issues and sub tasks, even though linked, they are in two different projects.
The bulk move operation can be performed on both standard issues and sub-task issues but you need to move the sub-task to a new issue type based on issue's parent project that it moved too.
More details on that here:
https://confluence.atlassian.com/display/Cloud/Modifying+Multiple+('Bulk')+Issues#ModifyingMultiple('Bulk')Issues-bulkmove
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.