We have an issue in our project Eg: issue1, which we removed from the sprint (Sprint 6) during the sprint, but it does not show in the sprint report in the section for removed from sprint nor in the Burndown chart (at all).
Could you please tell us what we do wrong - it makes it hard to use the reports.
Hi Vishal,
It could be that you're running into https://jira.atlassian.com/browse/JSWSERVER-14984.
Hi @Vishal ,
This issue was removed after the sprint started? Can you see the information removed from a sprint in the history of this issue?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
@Ollie Guan Please see the screen shot.
It happens often, this is just an example - and we can't figure out why it happends.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Online forums and learning are now in one easy-to-use experience.
By continuing, you accept the updated Community Terms of Use and acknowledge the Privacy Policy. Your public name, photo, and achievements may be publicly visible and available in search engines.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.