Sprint Burn-Down by Hours instead of by Story Points

Michael Green
Contributor
June 5, 2016

Hi,
Is it possible to do a Sprint Burndown chart that is based on tasks rather than story points ? And specifically hours on those task's original estimates rather than Story Points for the parent Story ?
Regards
Michael

1 answer

0 votes
Deleted user June 6, 2016

Yes you can! If you have the correct permission, go the "Board > Configuration > Columns > Estimation" then choose what setting do you like smile

Suggest an answer

Log in or Sign up to answer
TAGS
atlassian, loom, loom for training, loom for teaching, video training, async learning, online education, screen recording, loom tutorials, loom use cases, atlassian learning, team training tools, instructional video, virtual training tools

🛗 Elevate Your Training and Enablement with Loom

Join us June 26, 11am PT for a webinar with Atlassian Champion Robert Hean & Loom’s Brittany Soinski. Hear tips, stories, and get your burning questions answered. Learn how Loom makes training and enablement easier. Don’t miss it!

Register today
AUG Leaders

Atlassian Community Events