Story Points - Global Setting

Liam Rosewell February 8, 2022

Is it possible to set story points as the default instead of original time estimate, within stories/tasks and sub-tasks, as part of global settings so that you do not need to do it each time you create a new project board?

1 answer

0 votes
Pramodh M
Community Champion
February 8, 2022

@Liam Rosewell 

You need to change the context of story point field in Jira admin settings.

Choose all the issue types in context

https://support.atlassian.com/jira-cloud-administration/docs/edit-a-custom-field-context/

Thanks,

Pramodh

Suggest an answer

Log in or Sign up to answer
TAGS
atlassian, team '25 europe, atlassian event, barcelona 2025, jira, confluence, atlassian intelligence, rovo, ai-powered collaboration, developer tools, agile teams, digital transformation, teamwork solutions, atlassian conference, product announcements

🌆 Team '25 Europe registration is now open!

Join the largest European gathering of the Atlassian Community and reimagine what’s possible when great teams and transformative technology come together. Plus, grab your Super Fan ticket now and save over €1,000 on your pass before prices rise on 3 June.

Register now
AUG Leaders

Atlassian Community Events