Story points does not show on sprint board

Kendra Gaunt March 25, 2024

Question: How do I achieve seeing the story points on user stories and time-based estimates on the spike when in the sprint board view?

Context

  • Company-managed, Scrum board
  • Estimation method = story points
  • Time tracking = enabled

Story A in our active sprint does not show its story points on the card in the sprint board view. There are story points assigned to this story + subtasks w/ hours. Original estimate field = 0m.

Screenshot 2024-03-25 at 2.01.39 PM.png

What's strange is that story B in the same column (it also has story points + subtasks w/ hours, Original estimate field = 0m), shows the points in the sprint board view.

Screenshot 2024-03-25 at 2.11.27 PM.png

Additionally, I can see the Spikes w/ their time estimates on the board just fine.

Screenshot 2024-03-25 at 2.13.26 PM.png

When I look at the Sprint backlog view, the not started/in progress/completed point summary is correct - so nothing is missing.

THEN...

When I turn off time tracking (in board configuration) I can see the story points on story A, but all of the time estimates on the Spikes go away.

 

I would like to see story points on stories and time based estimates on spikes in the active sprint board view.

1 answer

1 accepted

0 votes
Answer accepted
Trudy Claspill
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
March 25, 2024

Hello @Kendra Gaunt 

Welcome to the Atlassian community.

You cannot configure the board to display different estimation options per issue type.

If you have the Estimation statistic set to Story and you have Time Tracking turned on, then what you see in the card is the Remaining Estimate for cards that have an Original Estimate.

Screenshot 2024-03-25 at 12.15.49 PM.png

In the above image my mouse is hovering over the "10m" bubble in the lower right corner.

 

If you want to see both Story Points and Original Estimate you can add those to the cards and separate fields, as I have done above. "5" is the Story points field and "5 hours" is the Original Estimates field.

Screenshot 2024-03-25 at 12.17.47 PM.png

Kendra Gaunt March 25, 2024

Ahh, gotcha! Thank you.

Kendra Gaunt March 25, 2024

Actually - to clarify... what's confusing is that this story does not have an original estimate. It just has story points - so why would it not show up?

 

I shared an example of another in sprint story and that one has the story points. There's nothing different between the 2 stories.

Trudy Claspill
Community Leader
Community Leader
Community Leaders are connectors, ambassadors, and mentors. On the online community, they serve as thought leaders, product experts, and moderators.
March 25, 2024

Ah, my mistake. I did some more experimenting and found the following:

Time will be shown in the bubble when Time Tracking is on and

  1. if there was a non-zero Original Estimate, or
  2. if there was a zero Original Estimate and some time has been logged.

The bubble is displaying Remaining Estimate, and gets an initial value based on the Original Estimate.

If there is not a non-zero Original Estimate than there is no Remaining Estimate to calculate. In that case it appears that Story Points will be shown in the bubble.

Like Kendra Gaunt likes this

Suggest an answer

Log in or Sign up to answer
DEPLOYMENT TYPE
CLOUD
PRODUCT PLAN
STANDARD
PERMISSIONS LEVEL
Product Admin
TAGS
AUG Leaders

Atlassian Community Events